Illustrative image – not actual.The Central Government cleared to the 13 km long Worli-Nariman Point sea link on 12 February 2003. The project, earlier scheduled to be completed by 2003 at a cost of Rs.1,465 crore has suffered time and cost overruns. It is now likely to be completed by 2006, at an estimated cost of Rs.3,000 crore.
Due to the delay in implementation of the project and alteration in the design the cost of the sea link is expected to increase. The project, would be executed on build, operate and transfer (BOT) basis
The 13 km freeway forms the second phase of the 17km Bandra-Worli-Nariman Point stretch. The first phase, the 4km Bandra-Worli sealink project, is currently under execution, albeit with considerable time and cost overruns. The project cost is estimated at Rs.800 crore, as against the original cost of Rs.400 crore. This project, originally expected to be commissioned by 2003, is running three years behind schedule.