Illustrative image – not actual.Of the 21 projects, Parej East and Hurilong projects could not be started due to non-grant of environment and forest clearances.
Another ongoing project Kalyani open cast project can be recommenced only after green clearances.
Of the remaining 18 projects, Amrapali OCP is on-schedule and other 17 are delayed due to problems such as authentication of land, forestry clearance and site hand over, environmental, coal evacuation problem, rehabilitation and resettlement (R&R) issues and safety reasons.
As on 31 March 2018, there are 21 ongoing and 34 completed mining projects under CCL, with sanctioned capacity of 112.85 million tonne. The sanctioned capital for the ongoing and completed projets is Rs 4,095.5 crore and Rs 3,023.21 crore respectively.