Illustrative image – not actual.The Central Electricity Authority (CEA) has urged the Union Ministry of Power to intervene in order to earmark a portion of the natural gas allocated from Reliance Industries' KG D-6 basin to the power sector for the Gujarat Government's 375 MW Utran extension combined cycle power project.
The CEA has requested expeditious gas-linkage as the project being developed by Gujarat State Electricity Corporation is due to be commissioned by November 2009, for which pre-commissioning activities have already been started.
The agency has stressed upon the urgent need to allocate about 2.0 mmscmd of gas to sustain the project's commissioning and testing activities, while around 1.21 mmscmd is to be required to operate the plant at 60.5 per cent plant load factor, following it's commissioning.