CEA rejects Farakka hydel project of NHPCIllustrative image – not actual.

National Hydroelectric Power Corporation had planned to set up a 125 MW Farakka Hydroelecotic project in Bengal.

NHPC had approached Central Electricity Authority for the techno-economic clearance, but CEA has returned the proposal on the grounds of the high cost. The proposal was rejected since the project cost was estimated at Rs.1,250.88 crore which works out to Rs.10 crore per MW. CEA has so far not cleared a single project at such a high cost.

NHPC has removed the details of the project from its website after it received the letter from CEA.

It is reportedly said that the Bengal government is likely to offer this project to National Thermal Power Corporation along with the 900 MW Purulia pumped storage venture. There is also a possibility that the state would offer it to private companies.