Illustrative image – not actual.The Central Electricity Authority (CEA)
has accorded techno-economic clearance to the 108 MW Kovilkallappal Combined
Cycle Power Project in Tamil Nadu. The Kovilkallappal Combined Cycle Gas
Turbine project is located at Tiruvanrur (Kovilkallappal) in Tamil Nadu and is promoted
by TNEB.
The project was earlier conceived as 30
MW plant, however, with increased availability of gas from Oil and Natural Gas
Commission wells, the capacity has been raised to 108 MW. The gas turbines
would be supplied by Bharat Heavy Electrical Limited (BHEL) who have been
awarded the turnkey contract for execution of the project. This will be a first
project for an advance class gas turbine being supplied by the BHEL.
The total completed cost of the project
is Rs. 289 crore. The project is being totally financed by debt. The Power
Finance Corporation would be financing Rs. 240 crore at a fixed interest of 15
per cent and repayment period of 15 years. The balance funding would be raised
through a bond issue.