CEA gives nod for Sawlakote, Kirthai-II power projectsIllustrative image – not actual.

The Central Electricity Authority (CEA) has given techno-economic clearance for construction of Sawlakote and Kirthai-II power projects in the state of Jammu and Kashmir.

The Sawlakote power project of 1,856 MW capacity will be constructed at a cost of Rs 22,000 crore, with a completion period of 10 years. The Kirthai-II power project of 930 MW capacity will be constructed at a cost of Rs 5,500 crore, with a completion period of six and a half years.

The J&K Power Development Corporation (PDC) had submitted the Detailed Project Reports (DPR) to the central body in 2014, for both the projects.

The projects will be constructed with a funding pattern of 70:30 ratios from financial institutions and the state government.

The Power Finance Corporation (PFC) has already committed to funding Rs 13,000 crore towards the Sawlakote project, while PDC will have to arrange the funding for Kirthai.

The projects are likely to be developed in engineering, procurement and construction (EPC) mode.

The state government is likely to negotiate with Sawlakote consortium comprising Ozaltn and Spas for development of the Sawlakote project.

 