The Central Electricity Authority (CEA) has accorded techno-economic clearance to the 150 MW extension power project of the Balimela Power Project being implemented by the Orissa Hydro Power Corporation in the Malkangiri district of Orissa.

 

The extension project entails the setting up of two units of 75 MW each at the existing power house that already has 360 MW of capacity through six units of 60 MW each. The two extension units would be commissioned at the end of 31 and 33 months, respectively.

 

The project has a total cost of Rs.200 crore and a debt-equity ratio of 60:40. The equity component of Rs.80 crore would be brought in by OHPC (Rs.60 crore) and the Orissa State government (Rs.20 crore). The debt portion of Rs.80 crore (including a foreign currency component of $21 million) would be financed by Power Finance Corporation.