Illustrative image – not actual.The Central Electricity Authority (CEA) has approved an additional 2 x 250 MW thermal generating capacity at Guru Hargobind thermal power station at Bathinda in Punjab. This would take the total capacity of the power station to 920 MW.
The project, to be implemented by Punjab State Electricity Board (PSEB) is estimated to cost Rs.1,790 crore, including an interest amount of Rs.278 crore. Of the total amount, the PSEB would bring in Rs.554 crore, while the Power Finance Corporation would arrange for the remaining amount of Rs.1,236 crore through loans.
Eastern Coal has also been tied up for the supply of 1.89 million tonnes per annum of coal for the project.
Bharat Heavy Electricals Ltd. would be the EPC contractor for the project.
The project has already received clearance from the state’s pollution control board, while final environmental clearance is awaited.