Illustrative image – not actual.The
Central Electricity Authority (CEA) has accorded techno-economic clearance for
the addition of a fifth 250 MW generating unit at Suratgarh Thermal Power
Station in the Sriganganagar district of Rajasthan. This is under the expansion
stage III, which will result in the achievement of a total installed capacity
of 1,250 MW at the power station.
Full power generation by the plant both
in terms of peak output and energy generation will be absorbed in Rajasthan.
The project to be executed by Rajasthan Rajya Vidyut Utpadan Nigam Limited has
been cleared by the CEA at a completed cost of Rs.752 crore including interest
during construction to the tune of Rs.99 crore. The debt equity ratio is proposed
at 80:20 with debt of Rs.448 crore coming from the Power Finance Corporation
(PFC) and a loan of Rs.150 crore to be raised from commercial banks.
The main plant package including the
boiler and generator has been awarded to the Bharat Heavy Electricals Limited (BHEL)
and the project shall be completed in 29 months from February 2001 -- the
zero date. The Ministry of Coal has given coal linkage of about 1.02
million tonnes per annum for Grade F coal, which is sufficient for the proposed
plant. The raw water requirement shall be met from the Indira Gandhi Main Canal
and land for the expansion project is already available. Ash storage facilities
created during Stage-I and Stage-II of the Suratgarh Thermal Power Project
would be sufficient for additional 250 megawatts under Stage-III.