Illustrative image – not actual.Central Coalfields (CCL) has obtained environment clearance from the Ministry of Environment & Forests (MoEF) for capacity expansion of the Piparwar opencast project in Jharkhand.
The total forest area involved in mining is 186.50 ha, for which Stage-1 forest clearance has been received. The company will enhance the capacity of the project from the existing 10 million tpa to 12.5 million tpa and from a peak capacity of 11.5 million tpa to 14.375 million tpa. The project entails an investment of Rs 1,093.65 crore.
The mining project has total geological reserves of 244 million tonne and mineable reserves of 48.80 million tonne.