The CCI, on 6 April 2011, approved highway projects in Gujarat and Rajasthan.

The committee has given a go-ahead to the six-laning of 102.3 km of NH 8 between Ahmedabad and Vadodara under the NHDP Phase V. The project is to be implemented on DBFOT basis under BOT (toll) mode of delivery. The project cost is estimated at Rs 2,537.76 crore and the concession period is 25 years including the construction period of 36 months. It will cover the districts of Ahmedabad, Kheda, Anand and Vadodara in Gujarat.

The four-laning of 88.09 km of NH 12 between Kota and Teendhar in Rajasthan was also approved by the CCI. The four-laning is being done under the NHDP Phase III on DBFOT basis in BOT mode of delivery. The total project cost is estimated at Rs 580.79 crore. The concession period is 25 years including construction period of 30 months.