CCI approval for six laning of Vadodara-Surat section in GujaratIllustrative image – not actual.

The Cabinet Committee on Infrastructure, on 26 April 2012, approved the six laning of Vadodara-Surat section on NH-8 in Gujarat under NHDP Phase V.

The 6.745-km project is to be implemented on DBFOT/BOT basis. The total cost of the project including land acquisition, rehabilitation and pre-construction activities will be Rs 509.29 crore. The concession period will be 12 years including construction period of 30 months. The main object of the project is to expedite the improvement of infrastructure in the state of Gujarat and also in reducing the time and cost of travel for traffic, particularly heavy traffic, plying between ‘Vadodara-Surat’.