Illustrative image – not actual.The CCEA has accorded approval to the North Eastern Electric Power Corporation (NEEPCO) for the implementation of the 100 MW Gas based power project in Tripura.
The power plant is estimated to entail an investment of Rs 421.01 crore. The project is expected to be funded with debt equity ratio of 70:30. The debt portion will be met through commercial borrowing and the equity portion will be met from internal resources of NEEPCO.
The project is scheduled for commissioning within 30 months from the date of investment approval. The entire power from the project is to be allocated to Tripura.