CCEA nod for Kribhco expansion soonIllustrative image – not actual.

Kribhco expects to move ahead with its Hazira unit expansion project in June 2005 or so. The Department of Fertilisers, it is learnt, is in the midst of preparing a fresh detailed note on the project. This note would be forwarded to the CCEA in the last week of May 2005, after which CCEA approval is expected.

The Rs.1,655 crore project entailing expanding of urea capacity by 10.56 lakh tpa and ammonia capacity by 6.1 lakh tpa has been fraught with inactivity since January 2004 when Public Investment Board approval was received.

Meanwhile, the company has floated bids inviting EPC contractors to the project. The selection would, however, be made only after CCEA clearance is received.

Regarding the means of financing, Kribhco has tied up with financial institutions for term loans of Rs.1,167 crore besides raising Rs.583 crore from internal accruals.