CCEA nod for Kiru Hydroelectric Project in Jammu and KashmirIllustrative image – not actual.

The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, has approved the investment sanction for construction of Kiru Hydroelectric Project Jammu and Kashmir. The investment will be made by Chenab Valley Power Projects (CVPPPL) for the project with a capacity of 624 MW.

The project will be implemented at an estimated cost of Rs 4,287.59 crore which includes Interest During Construction (IDC )and Foreign Component (FC) of Rs 426.16 crore and infusion of equity of Rs 630.28 crore by NHPC in CVPPPL for construction of hydroelectric power project including Rs 70 crore for pre-construction activities already approved by the Cabinet.

CVPPPL is a joint venture (JV) company amongst NHPC, the Jammu & Kashmir State Power Development Corporation (JKSPDC) and PTC with equity shareholding of 49 percent, 49 percent and two percent respectively.

The project is located on Chenab river in Kishtwar district of Jammu and Kashmir. It envisages construction of 135 mtr high concrete gravity dam above deepest foundation level, four pressure shaft of 5.5 mtr internal dia of length varying from 316 mtr to 322 mtr, underground power house and four tail race tunnel, horseshoe shape, seven mtr dia and length varying from 165 mtr to 190 mtr.

The project is envisaged as Run of River (RoR) Scheme, designed complying with the requirements of Indus Water Treaty 1960, with installed capacity 624 MW (four x 156 MW). The project will generate 2,272.02 MW in a 90 percent dependable year.

The foundation stone for the project was laid by Prime Minister Narendra Modi on 3 February 2019.