Illustrative image – not actual.On 21 November 2001, the Cabinet Committee on
Economic Affairs (CCEA) cleared the following proposals:
Jharkhand railway project:
The CCEA cleared a proposal for construction of a broad
gauge railway line between Koderma and Tilaiya in Jharkhand, at a cost of
Rs.307.62 crore. The line would be 68.2 km long.
The project would be funded through budgetary support
for the Railways. It is being set up for the supply of coal from the North
Karanpura coalfields to the thermal power plant being set up by National
Thermal Power Corporation at Barh.
Foreign equity in Barakhamba Sales:
The CCEA cleared a proposal for induction of 49 per cent foreign
equity in Barakhamba Sales & Services Pvt Ltd. The additional equity
would be utilised to fund the company’s cellular telecom services in the Andhra
Pradesh, Karnataka and Chennai circles.
The 49 per cent foreign equity amounts to Rs.9.8
crore in the company’s paid–up capital of Rs.20 crore. The remaining 51 per
cent equity would be brought in by Sterling Cellular Ltd (Rs.9.2 crore) and
Essar Shipping Ltd (Rs.1 crore). The CCEA approval is subject to the
condition that the foreign equity shall not exceed 49 per cent, and that
management control of the company shall be in the hands of resident Indians.
Revised cost
of CCL project:
The CCEA cleared the revised project report of
Central Coalfields Ltd’s Parej East Opencast project. The capital investment in
the project would now be Rs.162.88 crore. The project cost was originally fixed
at Rs.116.19 crore in March 1993.
The project,
located in the North Central Part of West Bokaro coalfields, is expected to be
completed by March 2002. The coal from this mine will be sent to Kedia and
Giddi washeries.
Revised cost of NLC projects:
The CCEA cleared the revised cost estimate of Neyveli
Lignite Corporation Ltd’s (NLC) Mine I Expansion project, which has shot up
from Rs.1,336.93 crore approved in March 1992, to Rs.1,658.38 crore. The
foreign exchange component in the revised cost is Rs.519.74 crore.
CCEA also cleared the revised cost estimate of NLC’s
first thermal power project at Neyveli in Tamil Nadu. The revised capital
investment would be Rs.1,420.27 crore, lower than the original cost of
Rs.1,590.58 crore. The reduced revised cost is on account of change in scope.
The revised estimate includes a foreign exchange component of Rs.547.74 crore.
Foreign equity in Uttam Steel:
The CCEA cleared Uttam Steel’s proposal for induction
of 25 per cent foreign equity, worth around Rs.800 crore. For details, click here.