CCEA clears second revised cost of Ranganadi hydel projectIllustrative image – not actual.

The Cabinet Committee on Economic Affairs (CCEA) has cleared the second revised cost estimate of Rs.1,455.55 crore at 1999 prices for the 3x135 MW Ranganadi hydel project, coming up in Arunachal Pradesh.

 

The project was first sanctioned in April 1987 at a cost of Rs.312.78 crore. This cost was revised to Rs.774.11 crore at 1993 prices in February 1995.

 

The hydel project, which is scheduled for completion by September 2001, has already incurred an expenditure of Rs.1,228.51 crore.