Illustrative image – not actual.The Cabinet Committee on Economic Affairs, on 22 September 2005, approved National Hydroelectric Power Corporation's 160 MW Teesta Low Dam Hydropower project (Stage IV) in West Bengal.
The total project cost, at March 2005 levels is Rs.1,061.38 crore , including interest during construction (IDC) component and financing charges of Rs.69.71 crore.
Seventy-five per cent of the equity would be provided by the Centre and the rest 25 per cent would be arranged by NHPC. The project is likely to be completed within 48 months after government approval.
The entire power generated from this project would be allocated to West Bengal, thus helping reduce the state's peaking power shortage.