Illustrative image – not actual.On 26 April 2001, the Cabinet Committee
on Economic Affairs (CCEA) approved the revised cost estimates of the
Moga-Hissar-Bhiwani and the Nathpa-Jhakri transmission line projects. These
projects are located in Haryana and Himachal Pradesh, respectively. The CCEA
also gave administrative sanctions for setting up units 3 and 4 of the Kaiga
Atomic Power Plant in Karnataka.
The revised costs of the two projects
are as follows:
|
Project |
Old Cost (Rs.crore) |
Year of Approval |
New Cost (Rs.crore) |
Project Status |
|
Moga-Hissar Bhiwani
Transmission Line (Haryana) |
890.0 |
1989 |
1561.6 |
Completed |
|
Nathpa-Jhakri Transmission Line
(Himachal Pradesh) |
95.2 |
1988 |
150.9 |
To be completed by May 2001 |
Units 3 and 4 of the Kaiga Atomic Power
Plant are being set up by Nuclear Power Corporation of India (NPCIL) at an
estimated cost of Rs.2856 crore. Each unit will have a capacity of 220 MWe.
Unit 3 is expected to be commissioned by October 2008 while Unit 4 would do so
by October 2009.