Illustrative image – not actual.The Cabinet Committee on Economic Affairs (CCEA) has approved the revised estimated cost of upgradation of Tanda to Raebareli section and Raebareli to Banda section of NH-232 in Uttar Pradesh.
The total cost for widening of NH-232 to two lane with paved shoulder from Tanda to Raebareli and from Raebareli to Banda on EPC mode, will be Rs 1,376.29 crore. The project, being developed by National Highways Authority of India (NHAI), is expected to be completed in 30 months from the date of commencement of work.
NHAI will implement the project in two separate packages. Under Package-I, it will develop Tanda to Raebareli road, while in Package-II, it will develop Raebareli to Banda road. Package-I, with a total length of 156 km, will entail an investment of Rs 817.52 crore. With 133 km length, Package-II will require an investment of Rs 558.77 crore.
The project covers the districts of Ambedkarnagar, Sultanpur, Raebareli, Fatehpur and Banda in Uttar Pradesh.