Illustrative image – not actual.The Cabinet Committee on Economic Affairs has approved the Rs.4,192 crore expansion plan of Neyveli Lignite Corporation.
The project involves the expansion of coal mining and power generation capacity. The project would be financed through a debt-equity ratio of 70:30. The debt portion of Rs.2,934 crore would have a foreign currency component of Rs.1,186 crore. The equity of Rs.1,257 crore would be raised through internal accruals.
The project aims at increasing the capacity of Mine II from 10.5 million tpa to 15 million tpa and that of power generation (linked to Mine II) from 1,470 MW to 1,970 MW. With this the total coal mining capacity of NLC would increase to 25.5 million tpa and that of thermal power generation to 2,990 MW.
NLC's power generation during 2003-04 was 16,389 million kwh, 9.1 per cent higher than the 14,970 kwh units generated in 2002-03. Lignite production stood at 2.06 million tonnes in 2003-04, up from 1.86 million tpa in the previous year.