CCEA approves fresh estimates for Mumbai Harbour and JNPT expansionIllustrative image – not actual.

The Cabinet Committee on Economic Affairs (CCEA) has approved fresh estimates for deepening and widening of Mumbai Harbour Channel and JN Port Channel (Phase-II).

The cost of the proposed project will be Rs 2,029 crore excluding the service tax. The entire project cost will be financed through internal resources of JN Port Trust (JNPT) with market borrowing, if required.

The project includes widening of the existing channel from 370 mtr to 450 mtr for straight reach; channel to be extended from 33.5 km to 35.5 km. The draft of the channel will be raised from 14 mtr to 15 mtr.

The work is likely to be executed by inviting global tenders. The project is to be completed within two years after being awarded.

The capacity of JNPT for container handling will be increased to 9.8 million twenty feet equivalent units (TEUs) once the fourth terminal becomes operational.

 