CCEA approves construction of bridges, flyovers under NHDP VIIIllustrative image – not actual.

On 6 December 2007, the Cabinet Committee on Economic Affairs gave its approval for construction of ring roads/bypasses (including improvement of NH links in city), grade separated intersections, flyovers, elevated roads, tunnels, road over bridges, underpasses and service roads at a cost of Rs.16,680 crore (Rs.6,302 crore from Government + Rs.10,378 crore from private sector), on BOT (toll) basis.

Out of Rs.16,680 crore of NHDP Phase-VII, Rs.10,500 crore will be spent on constructions for 700 km of ring roads and bypasses. The remaining amount of Rs.6,180 crore on stand alone grade separated intersections, road over bridges, elevated roads, tunnel, underpasses and service roads.

The contracts for stand alone ring roads and bypasses is expected to be awarded by March 2011 and scheduled for completion by December 2014.