CCEA approves Bihar road project Illustrative image – not actual.

The Cabinet Committee on Economic Affairs (CCEA) has approved four-laning of the 93 km Gaya-Hisua-Rajgir-Nalanda-Bihar sharif section on NH-82 in Bihar.


The project entails an investment of Rs 1,408.85 crore. Of the total cost, Rs 1,216.16 crore is the cost of civil construction and supervision works and Rs 192.69 crore is the cost of land acquisition, rehabilitation and pre-construction activities. The project is expected to be completed within three years of signing the contract agreement.


Meanwhile, Japan International Cooperation Agency (JICA) has agreed to provide loan assistance with 100 per cent financing for civil construction and supervision works for the project.

 