Illustrative image – not actual.During the first ten months of financial year 2025-26 (April to January), India’s interstate transmission system (ISTS) saw significantly higher transformation capacity being commissioned than the intrastate system (InSTS), according to the latest data from the Central Electricity Authority (CEA).
A total of 49,405 MVA of capacity was added on the ISTS network, compared with 29,458 MVA on the intrastate grid, making ISTS account for nearly 63 percent of the total 78,863 MVA commissioned during this period. This marks a reversal of the trend observed over the past three years, when more capacity was added within states. The unusual surge in ISTS capacity in FY26 is partly due to several projects originally scheduled for FY24 and FY25 being delayed and commissioned this year. Power Grid Corporation of India accounted for 41,005 MVA, more than twice its addition in the previous year, and contributed 52 percent of total capacity.
Private sector players, including Apraava Energy, Megha Engineering, Adani Energy Solutions, and Resonia, also supported ISTS expansion through TBCB projects, further bolstering interstate transmission infrastructure.