Illustrative image – not actual.Calico Resources Corporation has received a 16 year extension of time to construct a water system and apply water to beneficial use at its Grassy Mountain Project.
The new completion date for construction of the water system and application of water to beneficial use is October 1, 2028. During that time frame, Calico is authorized to use up to 2.0 cub ft per second (898 gallons per minute) of groundwater year-round for mining and industrial uses. As a condition of the extension, Calico will submit progress reports to Oregon Water Resources Department (OWRD) in 2017, 2022 and 2027 to provide evidence of diligence towards completion of the project, and the reports will be subject to public comment.