Illustrative image – not actual.Cairn India has put forward its proposal to the Directorate General of Hydrocarbons (DGH) for an extension of 10 years in the production sharing contract (PSC) for its Barmer block in Rajasthan.
However, the proposal has been turned down by the DGH and the company is likely to obtain an extension for only five years, since the block, according to the DGH, is primarily a crude oil producing block. An extension of 10 years is generally permitted for gas fields. The current PSC for the block is valid till 14 May, 2020.
Cairn India is planning to invest more than $ three billion (approx Rs 17,622 crore) over the next three years. For this investment, an extension of 10 years in the PSC is crucial.
In April 2013, the company had written to the Ministry of Petroleum & Natural Gas, that the PSC should be extended in the first instance till 2030, since the block had commercial production potential till 2040.