Cairn Energy invites pre-qualification bids for Annapurna gas fieldIllustrative image – not actual.

Cairn Energy India Pty Ltd has invited pre-qualification bids for front-end engineering and design study for the development of the Annapurna gas field in the KG-DWN-98/2 offshore block on the east coast of India.

 

The field water depth ranges from 800 to 1200 metres and is located 40 km offshore. The field is covered by 3D seismic and one well has been drilled and tested. A further appraisal well is in the drilling programme for August/September 2001. Subject to the results of the appraisal well, Cairn plans to enter into a contract in early October 2001 to undertake a phased development programme, which will identify the optimum development plan and its cost.

 

The contract deliverables would be:

 

Phase 1 Q4 2001

 

Initial study to identify the optimum development plan, the phasing and its cost to a level of +/- 15%. The duration of this study is likely to be 120 days.

 

Phase 2 Q1 & Q2 2002

 

Detailed development study that will be the basis for the Field Development Plan and will provide the scope of work for the preparation of tender documentation.

 

Phase 3 Q3 & Q4 2002

 

Preparation of tender packages and evaluation of tenders in anticipation of receiving project sanction by end-2002.

 

 

Initiation of phases 2 & 3 would be subject to the findings of phase 1 and would be at the option of Cairn.

 

Companies wishing to pre-qualify are required to submit bids by 24 August 2001.

 

Pre-qualification documents may be submitted to:


Principal Contracts Coordinator – East

Cairn Energy India Pty Ltd

Wellington Plaza, 2nd floor,

90 Anna Salai,

Chennai 600 002

India.

 

Ph: 91 44 855 5300

Fax: 91 44 855 5310

← All latest storiesBack to top →