The Cacora solid waste management plant in Goa is on track to become fully operational soon, reaching its full 100 tonne per day (TPD) capacity. Currently operating at 70 percent, the facility will begin processing all waste generated in surrounding areas to relieve pressure on the Saligao treatment plant.
The Goa Waste Management Corporation (GWMC) has addressed key challenges, including waste transportation logistics. Waste from four talukas— Quepem, Curchorem, Canacona, and Dharbandora— will be redirected to the plant. The government plans to procure specialised vehicles to avoid leachate spillage, a significant obstacle that earlier hindered full-capacity functioning. “We decided to add additional vehicles so that the waste generated in South Goa is shifted to the Cacora plant to meet its full capacity,” a senior official stated.
Built at a cost of Rs 173 crore, the facility spans 81,000 sq. mtrs., replacing a legacy waste dump cleared through bioremediation. Modeled on the Saligao plant but improved with updated design features, it complies with the Solid Waste Management Rules, 2016, and features separate lines for wet and dry waste, with an organic extruder at its core. The design was vetted by an expert committee for efficiency and compliance.