Cabinet nod to revised cost of Bhutan hydel projectIllustrative image – not actual.

The Cabinet has cleared the Revised Cost Estimate (RCE) of Rs 7,290.62 crore for the ongoing Hydroelectric Project (HEP) in Bhutan.

The total cost escalation for the project at the present stage is Rs 3,512.82 crore.

India had announced support for Bhutan's infrastructure building, adding that it would also get power from the hydel project.

The project will provide surplus power to India and thus augment power availability in the country enabling project works to proceed smoothly without interruption.

The bilateral agreement to execute the Punatsangchhu-II HEP was signed between India and Bhutan in April 2010, at the approved cost of Rs 3,777.8 crore, with funding by New Delhi as 30 percent grant and 70 percent loan, at 10 percent interest to be paid back in 30 equated semi-annual installments.