Illustrative image – not actual.The Cabinet Committee on Economic Affairs (CCEA) gave clearance to highway projects worth Rs.18,238 crore, including the six-laning of nine stretches under Phase V of the National Highways Development Programme (NHDP). The projects stretching to 1,409.93 km will be built on the Design, Build, Finance, Operate and Transfer (DBFOT) pattern.
The projects will be developed by the National Highways Authority of India (NHAI) through the PPP and the concessionaire will be selected by NHAI following two stage bidding process. The first stage of the bidding process i.e. pre-qualification of the bidders has already been completed. The second stage of bidding is underway.
Details of the projects are:
|
No. |
Section |
State | NH No. |
Length |
Total Project Cost including cost of LA, R&R, pre-construction (Rs.Crore) |
Concession Period including construction period of 30 months |
| 1 | Delhi-Agra | UP/Haryana | 2 | 179.10 | 2494.00 | 26 years |
| 2 | Kishangarh-Udaipur | Rajasthan | 79A, 79 & 76 | 315 | 3597.47 | 29 years |
| 3 | Chandikhol-Jagatpur-Bhubaneshwar | Orissa | 5 | 67.00 | 1104.00 | 27 years |
| 4 | Vijayawada-Elluru-Rajamundri | Andhra Pradesh | 5 | 198.20 | 2751.15 | 30 years |
| 5 | Varanasi-Aurangabad | UP | 2 | 192.40 | 2974.75 | 30 years |
| 6 | Nellore-Chilkaluripet | Andhra Pradesh | 5 | 183.7 | 2433.90 | 30 years |
| 7 | Krishnagiri-Walahjpet | Tamil Nadu | 46 | 148.30 | 1673.17 | 30 years |
| 8 | Belgaum-Dharwad | Karnataka | 4 | 80.18 | 707.61 | 30 years |
| 9 | Indore-Dewas | MP | 3 | 45.05 | 502.00 | 30 years |