Illustrative image – not actual.At a meeting held on 19 September, 2002, the Union
Cabinet approved the completion cost of the 1,020 MW Tala Hydroelectric Project
in Bhutan at Rs.3,580 crore with 60 per cent (Rs.2,148 crore) as grant and 40
per cent (Rs.1,432 crore) as loan.
It may be mentioned that the National Hydro-electric
Power Corporation has been mandated to execute the project while Water &
Power Consultancy Services would be rendering consultancy services. BHEL has
been selected for the supply of the Pelton turbines while the civil
construction contracts for the project has been awarded to Hindustan
Construction Company, Larsen & Toubro and Jaiprakash Industries.
The project is expected to be commissioned before September 2005. On completion, it would provide 1,020 MW peaking power to the Eastern Grid of India and 3,962 million units of electricity annually.