Illustrative image – not actual.Urbasolar SAS has undertaken construction of a new solar plant located near the town of Pâ in Burkina Faso.
The Emerging Africa Infrastructure Fund will finance 80 percent of construction of the project. The plant will supply electricity to Burkina Faso’s power utility, La Société National D’électricité Du Burkina Faso (SONABEL).
The ground-mounted photovoltaic power plant will have a peak power of 29,967.84 kWp. The PV modules will be installed on fixed structures with an inclination of 15 degree and oriented South.
The project includes string inverters and monocrystalline modules. The plant will be connected to the grid via a two km cable to a nearby sub-station.
The Emerging Africa Infrastructure Fund (EAIF) is the sole lender to the project and will provide EUR 29 million of the estimated EUR 35.4 million. Financial closure is expected by Q2/2021.
The Urbasolar project is one of the first of the new green energy plants. Around 280 MW is expected to be commissioned over the next three years.
Urbasolar was selected as the developer following a competitive tender process run by SONABEL. They will build and operate the plant, and construction is forecast to be completed within 18 months.
The Emerging Africa Infrastructure Fund will finance 80 percent of construction of the project. The plant will supply electricity to Burkina Faso’s power utility, La Société National D’électricité Du Burkina Faso (SONABEL).
The ground-mounted photovoltaic power plant will have a peak power of 29,967.84 kWp. The PV modules will be installed on fixed structures with an inclination of 15 degree and oriented South.
The project includes string inverters and monocrystalline modules. The plant will be connected to the grid via a two km cable to a nearby sub-station.
The Emerging Africa Infrastructure Fund (EAIF) is the sole lender to the project and will provide EUR 29 million of the estimated EUR 35.4 million. Financial closure is expected by Q2/2021.
The Urbasolar project is one of the first of the new green energy plants. Around 280 MW is expected to be commissioned over the next three years.
Urbasolar was selected as the developer following a competitive tender process run by SONABEL. They will build and operate the plant, and construction is forecast to be completed within 18 months.