Illustrative image – not actual.The government of Burkina Faso, a country in West Africa, through the Ministry of Energy has commenced construction of two solar power plants.
The first plant has a capacity of 20 MW in Koudougou, in Boulkiemdé province located in the country’s Centre-Ouest Region, and the other with a capacity of 10 MW in Kaya, in Sanmatenga province located in the Centre-Nord Region.
Engie, the French multinational electric utility company, will construct the parks.
The transmission lines and substations will be installed by Engie subsidiary Ineo Energy and Systems in collaboration with five other companies including India’s Mohan Energy Corporation and Unitech Power Transmission, Chinese entities TBEA and Shandong Taïkai Power Engineering and the IMPSDI consortium formed by China’s Inner Mongolia Electric Power Survey & Design Institute and Kenyan engineer Kesec.
The work on the solar plants will be completed between 12 to 14 months. The USD 73.5 million is funded by the Burkina Faso government with a World Bank loan.
The government also intends to strengthen three inter-urban links with electricity distribution stations.
A 83 km 225 kV transmission line will be built between the towns of Pâ and Diébougou while the second link, a 225 kV line will be constructed over a distance of 60 km connecting the towns of Ziniaré and Kaya, and the third link, a 90 kV line will link Wona and Dédougou which are 60 km apart.
The solar parks and the new infrastructure will inject 48.86 GWh which is around 2.5 percent of the nation’s demand into the electricity network and help stabilise the grid.
The first plant has a capacity of 20 MW in Koudougou, in Boulkiemdé province located in the country’s Centre-Ouest Region, and the other with a capacity of 10 MW in Kaya, in Sanmatenga province located in the Centre-Nord Region.
Engie, the French multinational electric utility company, will construct the parks.
The transmission lines and substations will be installed by Engie subsidiary Ineo Energy and Systems in collaboration with five other companies including India’s Mohan Energy Corporation and Unitech Power Transmission, Chinese entities TBEA and Shandong Taïkai Power Engineering and the IMPSDI consortium formed by China’s Inner Mongolia Electric Power Survey & Design Institute and Kenyan engineer Kesec.
The work on the solar plants will be completed between 12 to 14 months. The USD 73.5 million is funded by the Burkina Faso government with a World Bank loan.
The government also intends to strengthen three inter-urban links with electricity distribution stations.
A 83 km 225 kV transmission line will be built between the towns of Pâ and Diébougou while the second link, a 225 kV line will be constructed over a distance of 60 km connecting the towns of Ziniaré and Kaya, and the third link, a 90 kV line will link Wona and Dédougou which are 60 km apart.
The solar parks and the new infrastructure will inject 48.86 GWh which is around 2.5 percent of the nation’s demand into the electricity network and help stabilise the grid.