Illustrative image – not actual.
The Zimbabwe Power Company (ZPC) is anticipated to complete financial agreements with an Indian contractor in December 2021, allowing the Bulawayo Thermal Power Station re-powering project to begin in Q1/2022.
The plant is one of the country’s oldest, having been built by the Municipality of Bulawayo between 1947 and 1957 with an original installed capacity of 120 MW.
Despite having 11 kV and 33 kV cables connecting it to the national grid, the power station’s contribution to the grid is limited, needing refurbishment to give it a new lease of life.
Due to ageing plant equipment, the power station’s generating capacity has dwindled over time, with output dropping to around 30 MW per day from a revised 90 MW capacity and zero production on some days due to operational constraints.
In 2015, the government secured an initial finance pledge of USD 87 million from the India Exim Bank to fund the repowering project, with a further USD 23 million package bringing the total investment to USD 110 million.
However, in recent years, achieving financial closure, completing tender processes, and signing contracts have taken longer, delaying completion of the project.
However work procurement and contract negotiations were now complete, paving the way for project deployment in early 2022. The project’s procurement procedure was completed, and contract negotiations with the winning bidder BHEL were concluded.
The contract with BHEL must now be signed, together with financing arrangements for the total contract amount that have been confirmed.
ZPC would have created financing arrangements that are acceptable to both the contractor and Exim Bank of India by 31 December 2021. The project is expected to begin in H1/2022 when the financial drawdown is completed.
One of the major milestones in the repowering project would be the completion of a pipeline from Khami Dam to provide water to the station’s boilers.
This project is critical as the power plant requires extra water as one of its major fundamental components. The initiative is also projected to help in the recycling of Khami Dam sewer-contaminated water.
In 1987, the Bulawayo Power Station became part of the Zimbabwe Electricity Supply Authority (ZESA), which consolidated all local power companies.