Illustrative image – not actual.Bhilai Steel Plant, one of the four integrated steel plants of Steel Authority of India, has outlined a Rs.9,000 crore expansion programme.
The project aims at increasing overall finished steel capacity from the existing 4.9 million tpa to 7 million tpa, by 2012. A major change in product mix is also envisaged whereby the proportion of flat products (HR coils) would increase substantially. The entire project would be financed through internal accruals.
Of the total amount, Rs.5,000 crore would be spent during 2005-06 for a compact strip plant for the production of hot rolled coils besides setting up of a new steel melting shop, bar mill and continuous casting shop.
Mecon has been appointed consultant to the project. Mecon's project report is expected to be finalised by February 2004, after which it will be forwarded to IFCI for approval. BSP expects IFCI's approval to materialize within 4-5 months thereafter.
BSP's project is part of SAIL's overall expansion programme envisaging total capacity to reach 20 million tpa from the existing 13 million tpa, by 2012. The expansion project would cost around Rs.20,000 crore, at current prices.