BSNL's cellular services may be delayedIllustrative image – not actual.

The nationwide launch of Bharat Sanchar Nigam’s cellular mobile telecom services is likely to be delayed by at least one year, with the Union Communications and IT Minister, Mr Pramod Mahajan, reportedly asking for the cancellation of equipment and maintenance tenders floated by BSNL.

 

In January 2001, BSNL had floated equipment and maintenance tenders for four regional circles. Four entities - Motorola, Ericsson, ITI-Lucent and HFCL-Ericsson - had won tenders for the south, north, west and east circles, respectively.

 

Entity

Circle

No. of lines (lakh)

Motorola

South

14

Ericsson

North

13

ITI-Lucent

West

12

 

 

BSNL had issued advance purchase orders for the south, north and west circles. The east circle, where the HFCL-Ericsson combine had won, was left out. The Department of Telecommunications is planning to cancel the tenders for all three circles finalised earlier. Bids for the east circle, for which negotiations have been going on for around six months, would also be scrapped. Mr Mahajan has asked BSNL to begin the process of tendering and negotiations all over again.

 

It has also been reported that BSNL’s internal finance committee is of the view that the cellular services project would require an investment of around Rs.2,800 crore. On the other hand, the availability of funds with BSNL is only around Rs.780 crore.