BSNL to combine two GSM projectsIllustrative image – not actual.

Bharat Sanchar Nigam Ltd (BSNL) plans to combine its two global standard for mobile communication (GSM) projects, viz. its current requirement of 15 lakh GSM lines and an additional 25 lakh GSM lines in 2002, so as to bring in economies of scale and cut down project cost. With the consolidating of the two projects, the total project cost is estimated to be Rs.1,800 crore, whereas if the two projects were to be implemented separately, the total estimated cost would be around Rs.2,200 crore.

 

BSNL now plans to divide the consolidated 40 lakh GSM line project into four zones -- north, south, east and west.  Separate tenders would be invited for each zone.

 

In the first phase, BSNL plans to install 15 lakh lines by October 2001, while the remaining 25 lakh lines will be installed in the second phase.

 

Earlier, BSNL had planned to invite tenders worth Rs.800 crore for its 15 lakh GSM lines project in January 2001. Through this project, BSNL planned to provide cellular telephony to more than 600 cities and villages adjoining those cities in India. These lines would be used to provide telephony in both urban and rural areas and would cover important national and state highways.

← All latest storiesBack to top →