Illustrative image – not actual.BSES is making its exit from the 250 MW lignite-based power project at Srimushnal, in Tamil Nadu. BSES’s subsidiary Tamil Nadu Industries Captive Power Company was implementing the project. Losses of Rs.40 crore have been incurred on the project, without any progress being made.
The company had obtained administrative sanction for the acquisition of 280 hectares of land, and was making efforts to acquire the balance 436.40 hectare of land. It had also deposited Rs.4.61 crore with the Tamil Nadu government, towards the cost of the land.
BSES cited the reason of pulling out of the project, as the project was affecting the company’s resources, even though it had not taken off.
Reportedly, the reason to back out has come at a time when the company is reeling under heavy losses from its distribution ventures.