Illustrative image – not actual.The Maharashtra
State Eletricity Board (MSEB) stated that it would not grant clearance
under Section 44 of the Electricity (Supply) Act, 1928 for BSES’ 495 mw
Saphale combined cycle power project in Thane if the following conditions
were not fulfilled. These conditions were :
-
The power project should be set up
in two phases of 247 mw each.
-
BSES should pay Rs.9 crore to Tata
Electric Companies (TEC) as standby charges for the period during December
1998 and March 1999.
-
BSES should pay charges for 275 MVA
additional standby demand at the rate it (MSEB) would charge to TEC from
1 March 1999.