BSES Andhra Power to start commercial operations soonIllustrative image – not actual.

The 140 MW first phase of BSES Andhra Power Ltd's 220 MW gas based power project at Peddapuram will start commercial operations by the end of October 2001. This will be an open cycle system. While the second phase of 80 MW, i.e. the combined cycle phase, will start operations by February 2002.

 

Meanwhile, Gas Authority of India Ltd, with which the company has entered into an agreement for the supply of 1 million metric standard cubic metres per day of natural gas, will complete the 8 km long pipeline connecting the power plant and the main pipeline by 15 October 2001.

 

The company has already incurred a cost of around Rs.480 crore in the first phase of the power project, which is estimated to cost around Rs.700 crore. BSES holds 70 per cent of the equity in this project, while the remainder is shared by two civil contractors, viz. SCW Construction Ltd and Prasad Works Ltd.