Illustrative image – not actual.Brahmaputra Infra Power is implementing Bordikarai hydro electric power projects in Assam.
The company has invited tenders from eligible contractors for implementation of electromechanical packages of the project.
The selected entity's scope of envisages implementation of four nos (0.7 MW, 1.5 MW, 1.5 MW and 1 MW) of Bordikarai small hydro electric power project on EPC basis on existing canal of Bordikarai irrigation scheme. The major components are design, erection, testing etc of vertical axis semi hydro turbines with generators, with associated auxiliaries including EOT crane, cooling water system, 33 kV circuit breakers etc required for generation and evacuation of power at switchyard at each location.
The project has to be completed in 18 months from the date of award of contract.
The last date of submission of bids is 12 February 2010.
Related Links:
Tender
Project profile