BPL Power project to achieve financial closure by end of November 2000Illustrative image – not actual.

The 520 MW thermal power project, proposed to be set up by BPL Power at Ramagundam in Andhra Pradesh, is likely to achieve financial closure by the end of November 2000.

 

The Andhra Pradesh State government having agreed to provide a financial security package to the project, the formalities relating to project financing are expected to be complete within the next ten days. As per the agreement with the State government, the financial package would be activated thirty days before the date of commercial operations of the project.

 

ICICI, the lead debt financing arrangers, had set the condition of State government guarantee as a prerequisite for financial closure of the project.

 

The total cost of the project is estimated at Rs.2385 crore with a debt-equity ratio of 70:30. Marubeni and Electric Power Development Corporation of Japan have been appointed as the EPC and O&M contracts, respectively. These entities would have an equity stake of 26 per cent and 11 per cent, respectively, in the project.

 

The fuel supply agreement with Singareni Coal Collieries for 2.7 million tonnes of coal annually is expected to be finalised next week.