Illustrative image – not actual.The 520 MW thermal power project, proposed
to be set up by BPL Power at Ramagundam in Andhra Pradesh, is likely to achieve
financial closure by the end of November 2000.
The
Andhra Pradesh State government having agreed to provide a financial security
package to the project, the formalities relating to project financing are
expected to be complete within the next ten days. As per the agreement with the
State government, the financial package would be activated thirty days before
the date of commercial operations of the project.
ICICI,
the lead debt financing arrangers, had set the condition of State government
guarantee as a prerequisite for financial closure of the project.
The
total cost of the project is estimated at Rs.2385 crore with a debt-equity
ratio of 70:30. Marubeni and Electric Power Development Corporation of Japan
have been appointed as the EPC and O&M contracts, respectively. These
entities would have an equity stake of 26 per cent and 11 per cent,
respectively, in the project.
The
fuel supply agreement with Singareni Coal Collieries for 2.7 million tonnes of
coal annually is expected to be finalised next week.