Illustrative image – not actual.Bharat Petroleum Corporation (BPCL) has drawn up plans to invest Rs.1,200 crore to make automotive fuel that is compliant with Euro IV emission norms. The project is to be undertaken at its Mumbai (Mahul) Refinery, where an expansion programme is in progress.
BPCL is now in the process of finalising the project.
It may be noted that the capacity of the Mahul Refinery is being raised from 8.76 million tpa to 12 million tpa, entailing an investment of Rs.1,831 crore. An additional Rs.110 crore is being spent for producing cleaner petrol and Rs.318 crore to set up a unit to manufacture base oil. The expansion project would enable production of petrol and diesel that will meet Euro III norms.
Further, BPCL has finalised plans to extend the Mumbai-Manmad-Indore pipeline up to Delhi at a cost of Rs.750-800 crore. Work on the pipeline extension is likely to begin in the next few months with completion targeted within 24-30 months.