Illustrative image – not actual.The board of Bharat Petroleum Corporation, on 10 May 2006, approved the Rs.2,592 crore expansion-cum-modernisation project of its subsidiary, Kochi Refineries.
The project, already approved by the KRL board, envisages increasing the company's refining capacity from the present 7.5 million tpa to 9.5 million tpa. Mechanical completion is scheduled for September 2009. Once commissioned, the auto fuels (motor spirit and high-speed diesel) will conform to Euro III norms.
Besides, KRL's single point mooring facility at Puthuvypeen -- a vital component of the project -- is underway with completion scheduled for May 2007.