Bongaigaon thermal power station may miss deadlineIllustrative image – not actual.

NTPC is unlikely to commission the proposed 750 MW (3x250 MW) Bongaigaon thermal power station at Salakati in Assam during the Eleventh Plan (2007-12).

The company has reportedly blamed SPML Infra for sluggish civil works which may delay the Rs 3,750 crore project.

BHEL has erected one boiler and work for the second is underway. However, the turbines could not be installed as related civil construction was not done. The first two units of 250 MW each were to be commissioned in FY 2011-12.

In order to expedite the work, NTPC has decided to offload the balance civil works of Unit II and III. In November 2010, the company had invited tenders in this regard.

According to the revised commissioning targets set by NTPC, one 250 MW unit is slated to be operationalised by March 2012. Commissioning of the residual capacity is expected during the Twelfth Plan period (2012-17).