Bombay High Court puts all work on hold for Coastal Road ProjectIllustrative image – not actual.

The Bombay High Court has put a stay to the reclamation work for the coastal road project (Phase-I, Marine Drive to Worli) and has directed status quo.

The High Court observed that the reclamation of the coastal road will seriously affect and lead to irreversible ecological damage.

However, BMC noted that stopping of work will lead to a loss of Rs 10 crore each day to the public exchequer.

The court will hear five petitions with respect to the coastal road project. A public interest litigation (PIL) will be heard regarding the damage to Tata Garden Park in South Mumbai due to the road project.

The hearing of these petitions will begin from 23 April 2019.

The coastal road is proposed to directly connect Marine Drive and Kandivli. In 2018, work began on a 10 km stretch from Mumbai’s south to the Worli-end of Bandra-Worli Seal Link. It was also claimed that BMC had not obtained clearance from the Union Environment Ministry for the south Mumbai portion of the project. Around 168 ha is being proposed to be reclaimed for the project.

BMC had gone ahead with the project based on a 2015 change to rules that permitted construction of roads in coastal regulation zone areas in exceptional circumstances.

However, the bench stated that CRZ amendment does not justify the exceptional circumstances and also stated that no permissions had been obtained under the Wildlife Protection Act.

 