The Bangalore Metro Rail Corporation (BMRCL) will commence trial run on Kengeri Metro corridor from the end of March 2021. The completed third rail traction system will be energised in phases.
The Namma Metro’s six-km western extension from Mysuru Road to Kengeri (Purple Line) is on track. The commercial operations will start in June 2021 as per schedule. The travel time between Mysuru Road and Kengeri will be around 15 minutes.
The elevated section will have seven stations -- Nayandahalli, Rajarajeshwari Nagar, Jnanabharathi, Pattanagere, Mailasandra, Kengeri bus terminal and Challaghatta. The Challaghatta station is likely to be operational by March 2022.
All stations will have bus bays and crossover through the unpaid concourse area. The authority is planning foot-over-bridges (FOBs) at two locations by March 2022.
Solar panels will also be installed in these stations in due course, and tender for the same is being called.