BMRCL sets December 2014 deadline for Namma metroIllustrative image – not actual.

Bangalore Metro Rail Corporation (BMRCL), is likely to commission Phase-I of the Metro rail project by December 2014.

 

The project, launched during 2007, had its first deadline for phase-I in December 2011. After that, several deadlines have been overshot for reasons including land issues, litigation, changes and alteration in design and functioning, tardy contractors and so on. BMRCL now estimates that the 42.3 km Phase-I will be commissioned only by the end of 2014. However, the underground section of Phase-I is unlikely to begin commercial operations even by then because of a delay in the arrival of earth pressure balanced machines.

 

Commercial operations on the project, originally scheduled to begin in June 2012, were pushed to December 2013, then extended to March 2014, with December 2014 as the latest deadline.

 