Illustrative image – not actual.Bangalore Metro Rail Corporation (BMRC) will float tenders by October 2008 for electrical traction system of 33 km East- West and North - South rail corridors, estimated at Rs.728 crore.
By March 2009, BMRC is expected to spend Rs 1211.54 crore towards land acquisition, utility shifting, afforestation, constructing the ducts and stations, traction, civil works etc. Three foreign consultants from France, US and Japan have begun their work to oversee the construction and implementation of the project.
The entire 33 km phase one of metro network is scheduled to become operational by 2012. On completion of first phase, Bangalore Metro would be able to handle 40,000 passengers per hour. On any working day, the Banglore Metro is being designed to handle 10.20 lakh people.
BMRC will also float tenders for constructing the MG Road and Trinity circle stations with an investment of Rs.16.5 crore each. For eight other stations including Tollgate, Hosahalli, Vijayanagara, Yeshwanthpura, Soap factory, Mahalakshmi, R.V.Road terminal and Jayanagar tendering has already been given approval.